Coal, Gas and Transportation Commitments
NRG has entered into long-term contractual arrangements to procure fuel and transportation services for the Company's generation assets and for the years ended December 31, 2017, 2016, and 2015, the Company purchased $1.2 billion, $1.2 billion, and $1.8 billion, respectively, under such arrangements.
As of December 31, 2017, the Company's commitments under such outstanding agreements are as follows:
Period
(In millions)
2018
$
527

2019
188

2020
150

2021
112

2022
103

Thereafter
296

Total
$
1,376

Purchased Power Commitments
NRG has purchased power contracts of various quantities and durations that are not classified as derivative assets and liabilities and do not qualify as operating leases. These contracts are not included in the consolidated balance sheet as of December 31, 2017. Minimum purchase commitment obligations are as follows as of December 31, 2017:
Period
(In millions)
2018
$
21

2019
14

2020
12

2021
11

2022
10

Thereafter

Total (a)
$
68

(a)
As of December 31, 2017, the maximum remaining term under any individual purchased power contract is five years.
First Lien Structure
NRG has granted first liens to certain counterparties on a substantial portion of the Company's assets, excluding assets acquired in the GenOn and EME (including Midwest Generation) acquisitions, assets held by NRG Yield, Inc. and NRG's assets that have project-level financing, to reduce the amount of cash collateral and letters of credit that it would otherwise be required to post from time to time to support its obligations under out-of-the-money hedge agreements for forward sales of power or MWh equivalents. The Company's lien counterparties may have a claim on NRG's assets to the extent market prices exceed the hedged price. As of December 31, 2017, hedges under the first lien were in-the-money for NRG on a counterparty aggregate basis.
Lignite Contract with Texas Westmoreland Coal Co.
The Company's Limestone facility utilizes a blend of coal including lignite obtained from the Jewett mine, a surface mine adjacent to the Limestone facility, under a long-term contract with Texas Westmoreland Coal Co., or TWCC. The contract is a cost-plus arrangement with certain performance incentives and penalties. On August 18, 2016, NRG gave notice to TWCC terminating the active mining of lignite under the contract, effective on December 31, 2016.
Under the contract, TWCC continues to be responsible for reclamation activities. NRG is responsible for reclamation costs and has recorded an adequate ARO liability. The Railroad Commission of Texas has imposed a bond obligation of $95.5 million on TWCC for the reclamation of the mine. Pursuant to the contract with TWCC, NRG supports this obligation through surety bonds. Additionally, NRG is obligated to provide additional performance assurance if required by the Railroad Commission of Texas.